Table II    Summary Table for Key Information in the Reporting Month

 

Event

Event Details

Action Taken

Status

Remark

Number

Nature

Complaint received

2

Noise

Complaint investigation

Investigation report was submitted

Closed

Changes to the assumptions and key construction / operation activities recorded

0

---

N/A

N/A

---

Status of submissions under EP

3

Baseline Environmental Monitoring Report_v.2.0 (for Eastern  and Western Portal)

Submitted to EPD on 14 May 2008 (EP condition 3.2)

No comment from EPD

---

Monthly EM&A Report

(17th April to 28th April 08)

Submitted to EPD on 15 May 2008 (EP condition 3.3)

No comment from IEC

 

Baseline Environmental Monitoring Report_v.3.0 (for Western Portal)

Submitted to EPD on 22 May 2008 (EP condition 3.2)

Received comment from EPD on 29 May 2008

 

Notifications of any summons & prosecutions received

0

---

N/A

N/A

---


Future Key Issues:

Major site activities for the coming  month include:

Both Eastern  and Western Portal

  • Utilities diversion;
  • Soil nail works;
  • Pipe roofing works and installation of temporary facilities;
  • Boulder stabilization and soil slope.

Only at Western Portal

  • Marine works;
  • Site investigation;
  • Erection of SOR¡¦s Site office;
  • Excavation for slope cutting;
  • Shallow excavation and temporary support.