1.
This
is the 3rd
Environmental Monitoring and Audit (EM&A) Report prepared by Cinotech Consultants Limited for the ¡§Drainage Improvement in
2.
The
site activities undertaken in the reporting month included:
3. Environmental monitoring for the Project was performed in accordance with the updated EM&A Manual and the monitoring results were checked and reviewed. Site audits were conducted once per week. The implementation of the environmental mitigation measures, Event Action Plans and environmental complaint handling procedures were also checked.
4. Summary of the non-compliance of the reporting month is tabulated in Table I.
Table I Summary Table
for Non-compliance Recorded in the Reporting Month
|
Parameter |
No. of Exceedance |
No. of Exceedance Due to
the Project |
Action
Taken |
||
|
Action
Level |
Limit
Level |
Action
Level |
Limit
Level |
||
|
Eastern Portal |
|||||
|
1-hr TSP |
0 |
0 |
0 |
0 |
N/A |
|
24-hr TSP |
0 |
0 |
0 |
0 |
N/A |
|
Noise |
0 |
0 |
0 |
0 |
N/A |
|
Western Portal |
|||||
|
1-hr TSP |
0 |
0 |
0 |
0 |
N/A |
|
Noise |
0 |
0 |
0 |
0 |
N/A |
|
Water |
1 |
16 |
0 |
0 |
N/A |
Eastern
Portal
1-hour
TSP Monitoring
5. All 1-hour TSP monitoring was conducted as scheduled in the reporting month. No Action/Limit Level exceedance was recorded.
24-hour
TSP Monitoring
6. All 24-hour TSP monitoring was conducted as scheduled in the reporting month. No Action/Limit Level exceedance was recorded.
Construction
Noise
7.
All
construction noise monitoring was conducted as scheduled in the reporting month. No Action/Limit Level exceedance was recorded.
Western
Portal
8. All 1-hour TSP monitoring was conducted as scheduled in the reporting month. No Action/Limit Level exceedance was recorded.
24-hour TSP Monitoring
9. Baseline 24-hour TSP monitoring was conducted at Outside the Site Office at Western Portal (AQ3) in between 13 June to 26 June 2008.
Construction Noise
10. All construction noise monitoring
was conducted as scheduled in the reporting month. No Action/Limit Level exceedance was recorded.
Water Quality
11. All water quality monitoring was
conducted as scheduled in the reporting month except the monitoring at
mid-flood tide on 7 June 2008 that was cancelled due to Black Rainstorm
Warnings. In addition, monitoring on 25 and 27 June 2008 has been changed to 26
and 28 June 2008 due to Tropical Cyclone Warning Signals No. 8. One Action level and sixteen Limit level exceedances
were recorded. The exceedances
are considered due to the natural fluctuations but not due to the Project.
12. Licenses/Permits granted to the
Project include the Environmental Permit (EP) for the Project, An Environmental
Permit No. EP-272/2007 was issued on 26 April 2007 and Environmental Permit No.
EP-272/2007/A was issue on 26 October 2007. Later, the further Environmental
Permit (FEP-01/272/2007/A) was issued on 28 January 2008 to Dragages-Nishimatsu
Joint Venture as the Permit Holder.
13. Registration of Chemical Waste
Producer (License: 5213-148-D2393-02 for Eastern Portal and No.
5213-172-D2393-01 for Western Portal), Water
Discharge License (License No.: EP860/W10/XP0175 for Area of Mount Butler
Office and EP860/W10/XP0177 for Eastern Portal) and Construction Noise Permit
(License No.: GW-RS0114-08 for Eastern Portal and GW-RS0363-08 for Western Portal)
14. Summary of
key information in the reporting month is tabulated in Table II.
Table II Summary Table for Key
Information in the Reporting Month
|
Event |
Event
Details |
Action
Taken |
Status |
Remark |
|
|
Number |
Nature |
||||
|
Complaint
received |
0 |
--- |
N/A |
N/A |
--- |
|
Changes to the
assumptions and key construction / operation activities recorded |
0 |
--- |
N/A |
N/A |
--- |
|
Status of
submissions under EP |
2 |
Baseline Environmental Monitoring Report_v.4.0 (for Western Portal) |
Submitted to EPD on 8 July 2008 (EP condition 3.2) |
Verified by IEC |
--- |
|
Monthly EM&A Report (29th May to
31st May 08) |
Submitted to EPD on 11 June 2008 (EP condition 3.3) |
Verified by IEC |
|
||
|
Notifications of
any summons & prosecutions received |
0 |
--- |
N/A |
N/A |
--- |
|
Future Key Issues: |
|||||
|
Major site activities for the coming month include:
|
|||||