1.
This
is the 5th
Environmental Monitoring and Audit (EM&A) Report prepared by Cinotech
Consultants Limited for the ¡§Drainage Improvement in Northern Hong Kong Island ¡V Hong Kong West
Drainage Tunnel¡¨ (the
Project). This report documents the
findings of EM&A Works conducted in August 2008.
2.
The
site activities undertaken in the reporting month included:
3. Environmental monitoring for the Project was performed in accordance with the updated EM&A Manual and the monitoring results were checked and reviewed. Site audits were conducted once per week. The implementation of the environmental mitigation measures, Event Action Plans and environmental complaint handling procedures were also checked.
4. Summary of the non-compliance of the reporting month is tabulated in Table I.
Table I Summary Table
for Non-compliance Recorded in the Reporting Month
|
Parameter |
No. of Exceedance |
No. of Exceedance Due to the Project |
Action
Taken |
||
|
Action
Level |
Limit
Level |
Action
Level |
Limit
Level |
||
|
Eastern Portal |
|||||
|
1-hr TSP |
0 |
0 |
0 |
0 |
N/A |
|
24-hr TSP |
0 |
0 |
0 |
0 |
N/A |
|
Noise |
0 |
0 |
0 |
0 |
N/A |
|
Western Portal |
|||||
|
1-hr TSP |
0 |
0 |
0 |
0 |
N/A |
|
24-hr TSP |
0 |
0 |
0 |
0 |
N/A |
|
Noise |
0 |
0 |
0 |
0 |
N/A |
|
Water |
0 |
0 |
0 |
0 |
N/A |
Eastern
Portal
1-hour
TSP Monitoring
5. All 1-hour TSP monitoring was conducted as scheduled in the reporting month. No Action/Limit Level exceedance was recorded.
24-hour
TSP Monitoring
6. All 24-hour TSP monitoring was conducted as scheduled in the reporting month except the monitoring on 6 August 2008 has been changed to 7 August 2008 due to the hoisting of Tropical Cyclone Warning Signals No.8. No Action/Limit Level exceedance was recorded.
Construction
Noise
7.
All
construction noise monitoring was conducted as scheduled in the reporting month. No Action/Limit Level exceedance was
recorded.
Western
Portal
8. All 1-hour TSP monitoring was conducted as scheduled in the reporting month. No Action/Limit Level exceedance was recorded.
24-hour TSP Monitoring
9. All 24-hour TSP monitoring was conducted as scheduled in the reporting month except the monitoring on 6 August 2008 has been changed to 7 August 2008 due to the hoisting of Tropical Cyclone Warning Signals No.8. No Action/Limit Level exceedance was recorded.
Construction Noise
10. All construction noise monitoring
was conducted as scheduled in the reporting month. No Action/Limit Level exceedance was
recorded.
Water Quality
11. All water quality monitoring was
conducted as scheduled in the reporting month except the monitoring on 6 and 22
August 2008 due to the hoisting of Tropical Cyclone Warning Signals No.8 and
No.9 respectively. Water
Quality Monitoring was then re-scheduled to 7, 9 and 23 August 2008. No Action/Limit
Level exceedance was recorded.
12. Licenses/Permits granted to the
Project include the Environmental Permit (EP) for the Project, An Environmental
Permit No. EP-272/2007 was issued on 26 April 2007 and Environmental Permit No.
EP-272/2007/A was issue on 26 October 2007. Later, the further Environmental
Permit (FEP-01/272/2007/A) was issued on 28 January 2008 to Dragages-Nishimatsu
Joint Venture as the Permit Holder.
13. Registration of Chemical Waste
Producer (License: 5213-148-D2393-02 for Eastern Portal and No.
5213-172-D2393-01 for Western Portal), Water Discharge License (License No.: EP860/W10/XY0175 for Area of Mount Butler Office, EP860/W10/XY0177 for Eastern Portal and EP820/W9/XT086 for Western Portal) and Construction Noise Permit (License No.: GW-RS0114-08 for Eastern
Portal and GW-RS0363-08 for Western Portal)
14. Summary of
key information in the reporting month is tabulated in Table II.
Table II Summary Table for Key
Information in the Reporting Month
|
Event |
Event
Details |
Action
Taken |
Status |
Remark |
|
|
Number |
Nature |
||||
|
Complaint received |
0 |
--- |
N/A |
N/A |
--- |
|
Changes to the
assumptions and key construction / operation activities recorded |
0 |
--- |
N/A |
N/A |
--- |
|
Status of
submissions under EP |
1 |
Monthly EM&A Report (July 08) |
Submitted to EPD on 15 August 2008 (EP condition 3.3) |
Verified by IEC |
--- |
|
Notifications of
any summons & prosecutions received |
0 |
--- |
N/A |
N/A |
--- |
|
Future Key Issues: |
|||||
|
Major site activities for the coming month include:
|
|||||