1.
This
is the 9th
Environmental Monitoring and Audit (EM&A) Report prepared by Cinotech
Consultants Limited for the ¡§Drainage Improvement in Northern Hong Kong Island ¡V Hong Kong West
Drainage Tunnel¡¨ (the
Project). This report documents the
findings of EM&A Works conducted in December 2008.
2.
The
site activities undertaken in the reporting month included:
3. Environmental monitoring for the Project was performed in accordance with the updated EM&A Manual and the monitoring results were checked and reviewed. Site audits were conducted once per week. The implementation of the environmental mitigation measures, Event Action Plans and environmental complaint handling procedures were also checked.
4. Summary of the non-compliance of the reporting month is tabulated in Table I.
Table I Summary Table
for Non-compliance Recorded in the Reporting Month
|
Parameter |
No. of Exceedance |
No. of Exceedance Due to the Project |
Action
Taken |
||
|
Action
Level |
Limit
Level |
Action
Level |
Limit
Level |
||
|
Eastern Portal |
|||||
|
1-hr TSP |
0 |
0 |
0 |
0 |
N/A |
|
24-hr TSP |
0 |
0 |
0 |
0 |
N/A |
|
Noise |
0 |
0 |
0 |
0 |
N/A |
|
Western Portal |
|||||
|
1-hr TSP |
0 |
0 |
0 |
0 |
N/A |
|
24-hr TSP |
0 |
0 |
0 |
0 |
N/A |
|
Noise |
0 |
0 |
0 |
0 |
N/A |
|
Water |
0 |
0 |
0 |
0 |
N/A |
Eastern
Portal
1-hour
TSP Monitoring
5.
All 1-hour TSP monitoring was conducted as scheduled in the reporting
month. No Action/Limit Level
exceedance was recorded.
24-hour
TSP Monitoring
6.
All 1-hour TSP monitoring was conducted as scheduled in the reporting
month. No Action/Limit Level
exceedance was recorded.
Construction
Noise
7.
All construction noise monitoring was conducted as scheduled in the
reporting month. No Action/Limit
Level exceedance was recorded.
Western
Portal
8.
All 1-hour TSP monitoring was conducted as scheduled in the reporting
month. No Action/Limit Level
exceedance was recorded.
24-hour TSP Monitoring
9.
All 1-hour TSP monitoring was conducted as scheduled in the reporting
month. No Action/Limit Level exceedance
was recorded.
Construction Noise
10.
All construction noise monitoring was conducted as scheduled in the
reporting month. No Action/Limit
Level exceedance was recorded.
Water Quality
11.
All water quality monitoring was conducted as scheduled in the reporting
month. No Action/Limit Level exceedance was recorded.
12.
Licenses/Permits granted to the Project include the Environmental Permit
(EP) for the Project, An Environmental Permit No. EP-272/2007 was issued on 26
April 2007 and Environmental Permit No. EP-272/2007/A was issue on 26 October
2007. Later, the further Environmental Permit (FEP-01/272/2007/A) was issued on
28 January 2008 to Dragages-Nishimatsu Joint Venture as the Permit Holder.
13.
Registration of Chemical Waste Producer (License: 5213-148-D2393-02 for
Eastern Portal and No. 5213-172-D2393-01 for Western Portal), Water Discharge
License (License No.: EP860/W10/XY0175 for Area of Mount Butler Office,
EP860/W10/XY0177 for Eastern Portal, EP820/W9/XT086 for Western Portal and
EP680/W10/XY0183 for Intake W0) and Construction Noise Permit (License No.:
GW-RS0929-08 for Eastern Portal and GW-RS0894-08 for Western Portal).
14. Summary of
key information in the reporting month is tabulated in Table II.
Table II Summary Table for Key
Information in the Reporting Month
|
Event |
Event
Details |
Action
Taken |
Status |
Remark |
|
|
Number |
Nature |
||||
|
Complaint
received |
1 |
Construction works
conducted on Sunday at Western Portal |
Letter with complaint
investigation findings have submitted |
Verified by IEC |
--- |
|
Changes to the
assumptions and key construction / operation activities recorded |
0 |
--- |
N/A |
N/A |
--- |
|
Status of
submissions under EP |
1 |
Monthly EM&A Report (November 08) |
Submitted to EPD on 15 December 2008 (EP condition 3.3) |
Verified by IEC |
--- |
|
Notifications of
any summons & prosecutions received |
0 |
--- |
N/A |
N/A |
--- |
|
Future Key Issues: |
|||||
|
Major site activities for the coming month include:
|
|||||