Table II    Summary Table for Key Information in the Reporting Month

 

Event

Event Details

Action Taken

Status

Remark

Number

Nature

Complaint received

1

Construction works conducted on Sunday at Western Portal

Letter with complaint investigation findings have submitted

 

Verified by IEC

---

Changes to the assumptions and key construction / operation activities recorded

0

---

N/A

N/A

---

Status of submissions under EP

1

Monthly EM&A Report

(November 08)

 

Submitted to EPD on 15 December 2008 (EP condition 3.3)

 

Verified by IEC

---

Notifications of any summons & prosecutions received

0

---

N/A

N/A

---

Future Key Issues:

Major site activities for the coming  month include:

  • Tunnel excavation by blasting method, intake cofferdam and temporary cofferdam for River Channel at Eastern Portal;
  • Tunnel excavation by mechanical method, shallow and deep excavation and base slab construction at Western Portal;
  • Preliminary works, preparation works and temporary cofferdam at Intake W0;
  • Utilities trial pits and additional site investigation works at available intakes;
  • Casting of tunnel segments in China;
  • Test and disassembly in factory of West TBM; and
  • Assembly in factory of East TBM.