Table II    Summary Table for Key Information in the Reporting Month

 

Event

Event Details

Action Taken

Status

Remark

Number

Nature

Complaint received

1

Construction Noise at Eastern Portal

Complaint of Construction Noise at Early Morning at Eastern Portal Site (Letter with investigation findings was submitted)

Verified by IEC

---

Changes to the assumptions and key construction / operation activities recorded

0

---

N/A

N/A

---

Status of submissions under EP

1

Monthly EM&A Report

(January 2009)

 

Submitted to EPD on 14 February 2009 (EP condition 3.3)

 

Verified by IEC

---

Notifications of any summons & prosecutions received

0

---

N/A

N/A

---

Future Key Issues:

Major site activities for the coming  month include:

  • Tunnel invert concrete, temporary drainage diversion and temporary cofferdam for River Channel and site installation for TBM operation at Eastern Portal;
  • Tunnel invert concrete, TBM assembly, deep excavation and site installation for TBM operation at Western Portal;
  • Preliminary and design works, preparation works at Intake W0;
  • Utilities trial pits and additional site investigation works at available intakes;
  • Casting of tunnel segments in China;
  • Assembly & testing in factory and delivery and assembly on site of East TBM; and
  • Gantries and Conveyor erection for West Portal.