Table II    Summary Table for Key Information in the Reporting Month

 

Event

Event Details

Action Taken

Status

Remark

Number

Nature

Complaint received

0

---

N/A

N/A

---

Changes to the assumptions and key construction / operation activities recorded

0

---

N/A

N/A

---

Status of submissions under EP

1

Monthly EM&A Report

(July 2009)

 

Submitted to EPD on 26 August 2009 (EP condition 3.3)

 

 

Verified by IEC

---

Notifications of any summons & prosecutions received

0

---

N/A

N/A

---

Future Key Issues:

Major site activities for the coming  month include:

 

  • TBM excavation, site installation for TBM operation and permanent slope excavation for River Channel at Eastern Portal;
  • TBM excavation and site installation for TBM operation at Western Portal;
  • Excavation of intake structure at Intake W0;
  • Bend block supporting works and temporary cofferdam at Intake SM1;
  • Site preparation for Intakes THR2, HKU1, MB16 and PFLR1;
  • Pipelaying works along Mount Butler Road for Intake MB16;
  • Additional site investigation works at Intake BR6; and
  • Casting of tunnel segments in China.